# Build speed, not power price, decides how to power AI data centres

A computer model of 4,317 US sites finds that solar panels and batteries wired for direct current win in most places once lost computing time is priced in. The study is a preprint and has not been peer reviewed.

- Category: Efficiency
- Readiness level: III (Open source) on Science Underway's four-step scale, as proposed
- Published: 2026-11-13
- Editor: Stefan Perdal
- URL: https://scienceunderway.com/articles/build-speed-not-power-price-decides-how-to-power-ai-data-centres

## The study

Speed-to-Power Dominates Energy Costs for AI Data Centers: Technoeconomic Analysis of Powering AI in the Continental United States (preprint, not peer reviewed). arXiv 2611.17098. https://arxiv.org/abs/2611.17098

## At a glance

- What it shows: In a computer model of a large AI training data centre, solar panels with batteries came out cheapest in about 85% of US locations once the value of computing time lost during construction was counted. Wiring that system for direct current made it about 18% cheaper than the usual design.
- What it does not show: No real data centre has been built this way at this size. The headline result depends on assumed build times and an assumed value for an hour of chip time.
- Why it matters: AI firms are choosing power sources now, and waits to connect to the grid can exceed five years. The study offers one way to weigh speed against price on the same scale.

## What the study shows

The authors built an open-source cost model of four ways to power an AI training data centre with 100,000 GPUs, the chips that do the computing. The facility needs about 131 MW at peak. The four options were: solar plus batteries with conventional alternating-current (AC) wiring; solar plus batteries with direct-current (DC) wiring; an off-grid gas plant with diesel backup; and a normal grid connection. Each option was sized to deliver the same power, with 99% uptime, at each of 4,317 sites across the continental US. This is a simulation and a preprint that has not been peer reviewed.

Solar panels and batteries produce direct current. Most facilities convert it to AC with inverters and then back again inside the servers. Each conversion wastes some power. The authors report that keeping the whole system on DC cut lifetime energy cost by 18% on average, about 9 cents per kWh. The saving comes from fewer inverters and smaller losses along the way. For one West Texas site, they put the saving at about $570 million over the project's life.

On energy price alone, solar plus batteries was rarely the cheapest choice. A grid connection usually beat every off-grid option, although the authors say their grid cost leaves out upgrade costs and is a lower bound. Large gas plants also beat solar at big scale.

The authors then added a speed-adjusted cost. It charges each option for the computing lost while it is being built, priced at $2.40 per GPU-hour, the rental price for an H100 chip. Solar is assumed to take 2 years to build, gas about 4 years, and a grid connection 2.5 to 5 years depending on the state. On this basis, DC solar plus batteries was the cheapest option in about 85% of locations. The grid won in the rest, where power is cheap and connection is fast, such as New England and East Texas.

If gas plants could be built in 3 years, the picture shifts. DC solar stays cheapest in about 55% of locations, gas wins about 35%, mostly in cloudy regions such as the upper Midwest, and the grid about 9%.

Solar cost depended more on the worst run of cloudy days than on average sunshine. The system has to ride out the longest dull spell. Two sites with similar yearly sunlight, one in Colorado and one in foggy northern California, differed in cost nearly threefold.

## Our reading

In our reading, the paper makes two claims of different strength. The DC wiring result comes from engineering arithmetic: fewer conversions, less lost power, less equipment. The authors' checks show it holds unless DC equipment costs reach roughly twice their central estimate. It is the more durable finding.

The speed result depends on a pricing choice. It treats every idle GPU-hour as worth its rental price and adds that to the energy bill. The authors show where the answer flips. The break-even value between DC solar and the grid has a median of about $1.61 per GPU-hour, and ranges from under $1 to over $4 by location. So the verdict depends on what a given firm thinks an hour of its chips is worth.

A concrete case: a firm that values its chip time well below the rental price would find the grid competitive in more places. A lab that values its training runs above $2.40 an hour would find the argument for a fast-built solar site stronger still. The model lets each firm put in its own number, which is its main practical use.

The rest of the article (what it means, limits, what to watch) is free for members: https://scienceunderway.com/articles/build-speed-not-power-price-decides-how-to-power-ai-data-centres